Design Build Services for Colonial Road Improvements and Pocket Track Extension
Design Build Services for Colonial Road Improvements and Pocket Track Extension, Great Neck, Nassau County, NY, Furnish and Install Precast Bridge Arches over the LIRR Local Tracks.
Hicksville Station Improvements – Hicksville, New York
Hicksville Station Improvements – Hicksville, New York. Demolition of Existing Concrete Canopy; Installation of New Structural Steel Canopy, Stairs and Railings.
LaGuardia Airport Central Terminal Building Replacement Project
LaGuardia Airport Central Terminal Building Replacement Project - Queens NY Furnish and Install Interim and Final Cooling Towers.
Replacement of Rt110 Bridge Over Rt 27 – Babylon
Replacement of Rt110 Bridge Over Rt 27 - Babylon, NY Furnish and Install Precast Concrete NEXT Beams.
Rehabilitation of the 188th Street Bridge over the Grand Central Parkway
Rehabilitation of the 188th Street Bridge over the Grand Central Parkway; Queens, N.Y.; Install Precast Concrete Deck Panels Over the Grand Central Parkway and Perform Miscellaneous Structural Steel Repairs.
Atlantic Beach Bridge Over Reynold’s Channel Bascule Span Deck Replacement
Atlantic Beach Bridge Over Reynold's Channel Bascule Span Deck Replacement, Bridge Painting, Mechanical & Electrical Repairs. Temporary work platforms were installed for access. Components of the span lock machinery were replaced. The deck, purlins, and stringers were replaced while keeping the bridge in balance for on demand openings.
Replacement of Buckram Road Bridge – Locust Valley, New York
Furnish and Install New Railroad Bridge; Demolition of Existing Bridge. Project Required the preassembly of the new bridge prior to a one weekend complete replacement operation; Required the use of SPMT's and a two crane lift.
Replacement of Main Span Roadway and Approaches at the Bayonne Bridge
Replacement of Main Span Roadway and Approaches at the Bayonne Bridge; New York to New Jersey; Remove Existing Steel Super Structure for Both Approaches to the Bayonne Bridge. Work included demolition of structural steel over major local roadways.
Rehabilitation of the Rockaway Point Blvd Bridge – Rockaway NY
Installation of Temporary Acrow Bridge, Demolition of Existing Bridge and Replacement with New Bridge - All Structural Steel Work. Temporary Bridge was Launched into Position.
Erect Prestressed Concrete Box Beams over Barnum Creek
Erect Prestressed Concrete Box Beams over Barnum Creek, Install Misc. Structural Steel, Island Park, NY
Structural Rehabilitation of Rockaway Line Viaduct, Phase II, Jamaica Bay Crossing
Reconstruction of the existing concrete viaduct carrying the A train over Jamaica Bay. Work includes concrete T-beam repairs by removal of unsound concrete, installation of new reinforcing, forming of arched beam shape, and pumping new concrete as required to enlarge and encapsulate existing beams; overhead concrete spall repairs and removal of exisiting fiberglass forms. All work was performed over water from barges, floats and movable suspended platforms. New concrete was batched on a barge and pumped into place.
Goethals Bridge Replacement Project; New York to New Jersey
Removal of Structural Steel Approaches including removal over Local Roadways; Removal of Main Span by Strand Jacking to Barges Below; Associated Temporary Support and Jacking of Truss Side Spans and removal of Side Spans.
Erection of a pin connected two span Lens Truss Pedestrian Bridge over the west side highway in lower Manhattan
The Bridge was preassembled on barges in New York Harbor and off loaded to SMPT at Battery Park City. The bridge was moved to position and crane set during full roadway closures on weekend nights.
Restoration of Electrical & Mechanical Systems of Metropolitan Ave. Bridge
Restoration of Electrical & Mechanical Systems of Metropolitan Ave. Bridge over English Kill, Brooklyn, NY, Excavate, Form, Install Rebar, Place Concrete for new Generator Platform Footings. Furnish & Install Structural Steel & Grating for new Platform & SE Resistor Bank Platform. Remove & Reinstall all Bridge Mechanical & Electrical Machinery Components.
Reconstruction of the Throgs Neck Bridge Approach Spans
GCCOM replaced 130 foot long damaged girders, performed heat straightening of major structural members, performed structural steel repairs and installed the shield/work platform below the approach spans.
Throgs Neck Bridge Main Cable and Suspender Rope Investigation, Structural Steel Repairs, Painting and Catwalk Replacement
- Unwrap the main cable, take samples of individual main cable wires, splice in new individual wires, then re-wrap the main cable at four locations.
- Replace four suspender ropes.
- Replace the complete under deck catwalk system.
- Perform structural steel repairs.
- Install a 325,000SF shield / work platform directly beneath the bridge floor trusses
NYSDOT Meadowbrook and Loop Parkway Bascule Bridges
Replacement and repair of structural and operating components for both the Loop Parkway and Meadowbrook Parkway Bascule Bridges.
Reconstruction of the Gowanus Expressway Emergency Repair and Shore Parkway Interchange Interim Deck Replacement
Erection of fracture critical curved girders for a new HOV “fly over” lane. Erection of structural steel for widening portions of the Gowanus Expressway and one Exit Ramp. Jacking and shoring towers as required for the Structural work; and installation of both temporary and permanent structural bracing and new bearings.
Structural Rehabilitation of Rockaway Line Viaduct, Phase II, Jamaica Bay Crossing
Reconstruction of the existing concrete viaduct carrying the A train over Jamaica Bay.
Columbia University Suspension Bridge Main Cable Grant Study
GCCOM brought their cable compacting equipment and expertise to the Columbia University Civil Engineering Testing Lab and compacted and banded the world’s only physical model of a bridge suspension cable under tension.
KeySpan Citizens Gate Tunnel Structural Platforms Brooklyn, New York
Furnish and Install Structural Steel and Platform Grating at base of Gowanus Canal Gas Tunnel Shafts. All work was done in conformance with confined space regulations.
Rehabilitation of the Broadway/East New York Station Complex
Concrete demolition and spall repairs on underside of elevated station platforms.
Emergency Structural Steel Repairs to the 31st Bridge over I-278
Structural Steel Repair, Replacement, Temporary Support, and Jacking as required to repair the damage caused to the Bridge by an impact from an oversized vehicle using the expressway below.
Reconstruction of the 8th Street Bridge Access Ramp Over the Belt Parkway
Erection of new three span continuous, fracture critical, curved girders over the Belt Parkway with associated diaphragms and bearings. Final adjustment and welding of bearings.
West Thames Pedestrian Bridge
Erection of a pin connected two span Lens Truss Pedestrian Bridge over the west side highway in lower Manhattan.
Metropolitan Avenue Bridge Project
Restoration of Electrical & Mechanical Systems of Metropolitan Ave. Bridge over English Kill, Brooklyn, NY, Excavate, Form, Install Rebar, Place Concrete for new Generator Platform Footings.
Brooklyn Bridge Traveler Replacement
Furnish and install four new bridge traveler platforms, new structural steel tracks and supports, new machinery, and electrical contract rail system.